Note: Single-source report; awaiting corroboration.

On August 21, 2026, the Department of Energy (DOE) issued emergency order 202-26-40 under section 202(c) of the Federal Power Act, directed to PJM Interconnection, L.L.C. (PJM).

The order requires PJM to coordinate with Constellation Energy Corporation to keep Units 3 and 4 of the Eddystone Generating Station in Pennsylvania operational.

This directive ensures the units are available for operation, using economic dispatch practices to minimize costs for the American people.

The order takes effect August 23, 2026, and runs through November 20, 2026.