In Phase 1 of the Utility Energy Service Contract (UESC) process, an agency contacts the Federal Energy Management Program (FEMP) utility team or a federal project executive (FPE). This phase includes educational briefings, feasibility assessments, support service coordination, and securing management backing for the project.

The agency reviews procurement requirements specific to UESCs, which may include assembling an acquisition team, identifying review and approval processes, determining training needs, and establishing project priorities such as resilience and cybersecurity.

Next, the agency develops a plan of action outlining project motivations, site needs, utility selection procedures, and initial milestones. This plan also prepares for advanced technologies like combined heat and power and renewable energy.

The agency then prepares a limited acquisition plan addressing project-specific technical objectives and business requirements, ensuring compliance with agency acquisition policies. Best practices recommend an integrated team approach, including all relevant organizations and applying appropriate streamlining techniques to meet regulations.