The U.S. Department of Energy’s Oak Ridge Office of Environmental Management (OREM) and cleanup contractor United Cleanup Oak Ridge (UCOR) engineered an in-house repair for a specialized remote manipulator arm in Building 3029’s hot cells at Oak Ridge National Laboratory (ORNL), avoiding a potential six-month delay in the demolition project.
Building 3029, which supported radioisotope production for medical, industrial, and national defense purposes since the late 1940s, contains concrete-shielded hot cells designed for the safe handling of radioactive materials.
Identifying highly radioactive sources within these hot cells posed a significant challenge for completing the facility's demolition. According to Acting ORNL Portfolio Federal Project Director Michael Griswold, the team’s engineering solution enabled work to progress safely while mitigating extended schedule impacts.