On October 12, 2026, the U.S. Department of Energy (DOE) issued Order No. 202-26-50 under Section 202(c) of the Federal Power Act to PJM Interconnection, L.L.C. (PJM), following PJM's application submitted the previous day.
The order requires PJM to dispatch specified generating units and direct their operation to maintain grid reliability. PJM is also authorized to implement backup generation as a last resort before or during an Energy Emergency Alert (EEA) 3.
PJM may also instruct its Transmission Owners and Electric Distribution Companies to carry out the order as necessary to ensure system stability. The order is effective from October 13 through October 16, 2026.