Note: Single-source report; awaiting corroboration.

On November 20, 2026, the U.S. Department of Energy (DOE) issued emergency Order No. 202-26-52 under section 202(c) of the Federal Power Act to PJM Interconnection, L.L.C. (PJM).

The order directs PJM, in coordination with Constellation Energy Corporation, to ensure that Units 3 and 4 of the Eddystone Generating Station in Pennsylvania remain available to operate during the emergency period.

PJM is also required to use economic dispatch only during the hours necessary to meet the emergency, while minimizing costs to the American public.

This order is effective from November 21, 2026, through February 18, 2027.